Re: Target Costs of Production Orders

$
0
0

Hi Diana

 

I can think of 2 reasons

 

1. The GR is not done in the current period for this production order

 

2. The standard cost was deleted before the GR from this production order. Check when the present standard cost was released or is it blank as of now (field MBEW-LPLPR

 

Br. Ajay M